Factory completed
Dr Graham Cooley, CEO at ITM Power, pointed out that the facility is not only the largest in the world, but also has been designed and fitted out to include the latest state-of-the-art technology and semi-automated machines. The project also included an extension to the existing offices as well as the stack manufacturing and production areas. As part of the project, the team also created a ATEX rated test zone for factory acceptance that is coupled to a 5MW power supply on site.
As Oliver Jenkins, business development manager at Clegg, noted, the improvements to the factory will enable ITM Power to reach the production capacity of 1GW